3
Submitted/Shortlisted
11
Active / In Discussion
2
Passed / Declined
7
No Submission / Infeasible
15,000+
Total Jobs (all projects)
$21B+
Total Investment (all projects)
Submitted / Shortlisted
Active / In Discussion
Passed or Declined
No Submission / Infeasible
Showing 23 of 23

Project Savannah

Shortlisted Pharmaceutical / Drug Manufacturing
RFI Date: August 2024
Source: Texas Governor's Office EDT
Site: ~200 acres / 1M sf at TriTexas Logistics Park
Investment: Not disclosed
Jobs: Not disclosed

Operations

API (active pharmaceutical ingredient) chemical synthesis and monoclonal antibody (mAb) production. Major biopharmaceutical manufacturing facility.

Water / Wastewater

350,000 GPD water demand (Phase 1). Wastewater discharge characteristics not fully specified; wastewater pretreatment would be required by city.

Infrastructure Needs

Large water and wastewater capacity. City indicated water/wastewater improvements were planned and could meet project timeline, conditioned on pretreatment.

City of San Marcos Response

City confirmed that water and wastewater improvements were planned and could meet the project timeline. However, wastewater from pharmaceutical manufacturing would require pretreatment before discharge to city sewer.

Source: Governor's Office RFI documents, August 2024

Project Vortex Wind

Energy Storage / Automotive Battery Manufacturing
RFI Date: April 2025
Source: Texas Governor's Office EDT
Site Need: 100–150 acres greenfield OR 2.2M RSF existing building
Investment: $2.3 billion
Jobs: 2,000
NAICS: 335911

Operations

Energy storage systems and automotive battery cell and pack assembly. One of the largest projects by investment dollar amount.

Water / Wastewater

Water demand not specified in documents reviewed. Wastewater service was NOT available at the Axis site at time of RFI.

Infrastructure Needs

City confirmed 12-inch water main available. Wastewater service does not currently extend to site - significant infrastructure gap identified.

City of San Marcos Response

City confirmed a 12-inch water main is available near the site. However, wastewater service is NOT at the site - a critical infrastructure gap. City did not indicate when wastewater would be extended.

  • $2.3B investment makes this one of the highest-value prospects in the pipeline.
  • 2,000 jobs would be significant for San Marcos / Hays County.
  • Wastewater gap is a major feasibility concern.
Source: Governor's Office RFI documents, April 2025

Project Frontier

Active Architectural Products Manufacturing
RFI Date: May 2025
Source: Texas Governor's Office EDT
Site Need: 60–80 acres greenfield
Investment: $178 million
Jobs: 104–176

Operations

Architectural products manufacturing. Major air permit required - VOC emissions of 78.46 tons/year. Rail access preferred.

Water / Wastewater

216,300 GPD water demand. 173,040 GPD wastewater. Standard industrial profile without noted pretreatment concerns.

Infrastructure Needs

Rail access preferred. Major air quality permit needed from TCEQ. City confirmed Axis site can accommodate usage.

City of San Marcos Response

City confirmed the Axis site can accommodate the water and wastewater usage requested. No major infrastructure concerns identified by city staff.

  • VOC emissions of 78.46 tons/year will require a major TCEQ air quality permit - potentially a significant hurdle.
  • Rail preference aligns with Axis site's proximity to Union Pacific line.
Source: Governor's Office RFI documents, May 2025

Project Matcha Latte

Active Ceramic / Building Materials Manufacturing (Italian company)
RFI Date: May 2025
Source: Texas Governor's Office EDT
Site Need: 275,000 sf on 100 acres
Investment: $34.5 million
Jobs: 50
NAICS: 32530201

Operations

Outdoor porcelain pavers and dry mix base materials. Italian company. NAICS 32530201 (ceramic tile / stone products).

Water / Wastewater

50,000 GPD water. 40,000 GPD wastewater containing ceramic slurry - requires pretreatment before city sewer discharge.

Financing Status

Financing is NOT finalized - noted explicitly in RFI documents. Project feasibility contingent on securing funding.

City of San Marcos Response

Ceramic slurry in wastewater would require pretreatment. City reviewed water and wastewater capacity; no major capacity objection but pretreatment requirement is a condition.

  • Financing not finalized is a significant risk factor at this stage.
  • Smallest investment of any active project ($34.5M).
  • Ceramic slurry wastewater pretreatment adds cost and complexity.
Source: Governor's Office RFI documents, May 2025

Project America Flag

Shortlisted Tire Manufacturing (UK company seeking US HQ)
RFI Date: June–July 2025
Source: Texas Governor's Office EDT
Site: TriTexas Logistics Park shortlisted
Investment: Not disclosed
Jobs: Not disclosed
NAICS: 326211 (Tire Manufacturing)

Operations

UK-headquartered tire manufacturer establishing US global headquarters. NAICS 326211. Seeking US manufacturing footprint.

Water / Wastewater

189,271 m³/year water consumption (consumptive use, minimal discharge). Closed-loop gray water recycling system - low wastewater impact.

Infrastructure Needs

Primarily water supply. Closed-loop system reduces wastewater demands significantly compared to similar-scale manufacturers.

City of San Marcos Response

Axis site was shortlisted by the company. City response details not fully documented in available records. The closed-loop gray water recycling design is favorable for city infrastructure.

  • Formally shortlisted - one of two projects with confirmed shortlist status alongside Project Savannah.
  • 189,271 m³/year = approximately 137,000 GPD - moderate water demand.
  • UK company establishing US global HQ suggests long-term investment commitment.
Source: Governor's Office RFI documents, June–July 2025

Project Thomas Train

Active Energy / Power Generation (Fortune 100 Company)
RFI Date: July 2025
Source: Texas Governor's Office EDT
Site Need: 2,000 acres
Investment: Not disclosed
Jobs: Not disclosed

Operations

Combined cycle gas turbines (CCGT) dedicated to powering data centers. Fortune 100 energy company. Requires 2,000 acres - the largest land footprint of any prospect.

Water / Wastewater

870,000 GPD water demand. 480,000 GPD wastewater. Among the highest water demands in the project pipeline.

Infrastructure Concerns

City: water available for the portion of site within city service territory. Wastewater collection infrastructure does not exist at site but improvements are possible.

City of San Marcos Response

City confirmed water is available for the portion of the site within the city's service territory. Wastewater collection infrastructure does not currently exist at the site, but improvements are possible. The 2,000-acre requirement raises feasibility questions about whether the full site can be served.

  • At 2,000 acres, this project would require nearly the entire TriTexas Logistics Park footprint.
  • Fortune 100 company - significant economic weight but extraordinary infrastructure demands.
  • CCGT power generation for data centers is a growing sector with long-term demand.
Source: Governor's Office RFI documents, July 2025

Project Golden Eagle Sun

Infeasible - No Submission Solar Manufacturing
RFI Date: December 2025 / January 2026
Source: Texas Governor's Office EDT
Site Need: 300,000+ sf existing building
Investment: Not disclosed
Jobs: Not disclosed
Required Power: 15+ MW

Operations

Solar panel manufacturing. Required an existing building of 300,000+ sf. TriTexas Logistics Park is a greenfield site with no existing structures.

Water / Wastewater

1,000,000 GPD water by March 2026. City confirmed water capacity available in principle.

Decision Timeline

Required operational facility by March 2026. Greenfield development at Axis requires 12–18 months from permitting - physically impossible to meet deadline.

City of San Marcos Response

City confirmed water capacity was available but noted that Axis is a greenfield site. A new facility would require 12–18 months from permitting to completion - the March 2026 deadline was not feasible. No submission made for this project.

  • Eliminated due to timeline mismatch, not infrastructure capacity.
  • Needed existing building; Axis has none.
Source: Governor's Office RFI documents, December 2025 / January 2026

Project Lassen

Active / Under Evaluation Industrial Manufacturing (high-salinity wastewater)
RFI Date: December 2025
Source: Site Selector (Scout Cities)
Sites Shortlisted: TriTexas Logistics Park AND San Marcos Business Park
Investment: Not disclosed
Jobs: Not disclosed

Operations

Industrial manufacturing generating high-salinity (NaCl) industrial wastewater. Nonhazardous. Industry type not specified beyond wastewater characteristics.

Water / Wastewater

150,000 GPD industrial wastewater (nonhazardous, high salt/NaCl content). Wastewater characteristics may require pretreatment for city sewer.

Site Competition

Both TriTexas Logistics Park and San Marcos Business Park shortlisted. Competing internally within San Marcos for the project.

City of San Marcos Response

City staff noted 150,000 GPD is not unusually high and indicated they would double-check capacity. High-salinity wastewater (NaCl) would likely require evaluation of impacts on wastewater treatment plant operations.

  • Notable: two San Marcos sites competing for same project - Axis vs. Business Park.
  • Site selector firm Scout Cities involved, suggesting company identity is being shielded at this stage.
Source: Governor's Office RFI / Scout Cities documents, December 2025

Project Horizon Mill B

No Submission - City Could Not Support Steel Manufacturing / Direct Reduced Iron (DRI)
RFI Date: January 2026
Source: Texas Governor's Office EDT
Site Need: 900 acres
Investment: Not disclosed
Jobs: Not disclosed
NAICS: 3311 (Iron and Steel Mills)

Operations

U.S. steel company. Integrated steel mill + DRI (direct reduced iron) facility. NAICS 3311. Requires 900 acres.

Water / Wastewater

9,000,000 GPD (9 MGD) water demand. 1,300,000 GPD (1.3 MGD) wastewater. City's total water usage is approximately 18 MGD - this project alone would require ~50% of city supply.

City Decision

Moved to No Submission. Water demand is physically impossible to meet without massive regional infrastructure investment.

City of San Marcos Response

City determined it could not support this project. 9 MGD water demand equals approximately half of the city's total water usage. No submission was made.

  • The most water-intensive prospect in the pipeline by a wide margin.
  • City correctly identified this as infeasible without major regional water supply expansion.
Source: Governor's Office RFI documents, January 2026

Project Star

No Submission - City Could Not Support High-Tech Manufacturing (Solar / Semiconductor)
RFI Date: February 2026
Source: Texas Governor's Office EDT
Site Need: 700+ acres
Investment: $2 billion
Jobs: 675 Year 1 / 2,500 within 3–5 years
Decision Date: March 31, 2026
Target Production Start: March 1, 2027

Operations

High-tech manufacturing. Job types include metallization, PECVD, PVD (physical vapor deposition), and laser cutting - consistent with solar panel or semiconductor manufacturing.

Water / Wastewater

Large water demand (exact figure not specified in summary). City Utilities Director explicitly stated the city cannot support the requested water usage on a one-year timeline.

City Decision

Utilities Director: "We cannot support with that much water usage just a year from now. Have to pass."

City of San Marcos Response

City Utilities Director determined the city cannot support the project's water demands within the one-year timeline to production start. No submission made. Decision was driven by infrastructure timeline, not permanent capacity limitations.

  • $2B investment and 2,500 jobs would have been transformative for Hays County.
  • March 2027 production start was likely the fatal constraint - insufficient time to build out water infrastructure.
  • PECVD/PVD job types strongly suggest solar panel or semiconductor chip manufacturing.
Source: Governor's Office RFI documents, February 2026

Project Mount Fuji

Active - Site Tour Completed Chemical Manufacturing - High Purity Magnesium Oxide (Japanese company)
RFI Date: December 2025 / March 2026
Source: Texas Governor's Office EDT
Site: TriTexas Logistics Park shortlisted; site tour March 17, 2026
Investment: Not disclosed
Jobs: Not disclosed

Operations

Japanese company. Produces high-purity magnesium oxide (MgO). Specialty chemical manufacturing with industrial and electronics applications.

Water / Wastewater

47,560 GPD water. 3,700 GPD sewage. Among the smallest water/wastewater footprints in the pipeline - well within city capacity.

Infrastructure Notes

City: 12-inch waterline should be sufficient for their needs but only serves a portion of the site - extension may be needed depending on building location.

City of San Marcos Response

City confirmed the 12-inch waterline near the site should be sufficient for the project's water demand. Caveat: the line only serves part of the site; infrastructure extension may be needed. Wastewater demand (3,700 GPD) is minimal.

  • Site tour on March 17, 2026 indicates serious interest and active evaluation.
  • Very low water and wastewater demand - no infrastructure capacity concerns.
  • Japanese company entry suggests international manufacturing diversification interest in Central Texas.
Source: Governor's Office RFI / site tour documents, December 2025 – March 2026

Project North Star

Active - Decision July/August 2026 Advanced Magnetics Manufacturing (U.S. company)
RFI Date: March 2026
Source: Texas Governor's Office EDT
Site Need: Not specified (10,000 MT annual capacity)
Investment: $1.8 billion
Jobs: 700 (197 within 2–3 years)
NAICS: 3346 (Magnetic & Optical Media Mfg.)
Decision Date: July / August 2026
Production Start: Q2 2029

Operations

U.S. magnetics company producing "world's first high-performance rare-earth-free permanent magnets." 10,000 metric tons annual capacity. Strategically important for defense and EV supply chain.

Water / Wastewater

1,400,000 GPD (1.4 MGD) water. 800,000 GPD (0.8 MGD) wastewater. City notes water is "high but manageable" and encourages water reuse. Wastewater deemed acceptable.

Critical Infrastructure Note

SH 80 Lift Station (wastewater) completion updated to Summer 2028 per city email - aligns with Q2 2029 production start. Previously estimated 2029; now accelerated.

City of San Marcos Response

City finds water demand "high but manageable" and encourages water reuse strategies. Wastewater is acceptable. SH 80 Lift Station CIP completion updated to Summer 2028, which supports the Q2 2029 production start timeline. Site visit expected April/May 2026.

  • Most strategically significant project in pipeline: rare-earth-free magnets are critical for EV motors, wind turbines, and defense applications - currently dominated by Chinese supply chain.
  • Q2 2029 production start provides more realistic infrastructure runway than most other projects.
  • $1.8B investment and 700 jobs - second largest by investment in the active pipeline.
  • Site visit expected April/May 2026; final decision July/August 2026.
Source: Governor's Office RFI / North Star emails, March 2026

Project Vista Prism

Active - In Discussion Electronics Manufacturing (international company - possibly Sony, Panasonic, or Sharp)
RFI Date: March 2026
Source: Texas Governor's Office EDT
Site Need: 500+ acres greenfield; 2.9M sf per building (2 buildings)
Investment: Not disclosed
Jobs: Not disclosed
Power Demand: 153.1 MW electricity

Operations

International electronics company. Potentially Sony, Panasonic, or Sharp based on company profile. Two buildings of ~2.9M sf each - massive manufacturing campus.

Water / Wastewater

576,700 gallons/hour in Phases 2 & 3 (~13.8 MGD at peak). This approaches Project Horizon Mill B levels and represents a very large fraction of city water supply.

Power Demand

153.1 MW electricity demand - an extraordinary power requirement that would need direct coordination with ERCOT/utility provider. Larger than many small cities' entire power consumption.

City of San Marcos Response

Still in discussion as of March 2026. The massive water demand (potentially 13+ MGD at peak) and 153 MW power requirement would present extraordinary infrastructure challenges. No formal city determination documented yet.

  • If the 576,700 gal/hour figure is peak usage across phases, it equals ~13.8 MGD - roughly 75% of the city's total water supply capacity.
  • 153 MW power demand would require dedicated transmission infrastructure.
  • Two buildings of 2.9M sf each = ~5.8M total sf - by far the largest footprint in the pipeline.
  • Still in early discussion; no city feasibility determination yet.
Source: Governor's Office RFI documents, March 2026

Project Apex Graphite (Apex Anode Plant)

Rejected May 8, 2026 Battery Materials - Graphite Anode Refining
RFI Date: April 2026 (site tour April 7)
Company: Allied Graphite (formerly Urbix)
Site Need: 50 ac Phase 1 → 100–130 ac total
Investment: $207.4M Phase 1 / up to $584M total
Jobs: 156 → up to 448 ($80,338 avg.)

Operations

Refines raw graphite into coated spherical purified graphite (CSPG), an anode input material for lithium-ion batteries - not battery cell manufacturing itself. Partnered with Brazilian graphite producer Graphcoa. Ran through site-selection contractor JLL. Previously scouted the site in 2024 as "Project Chestnut" but was tied to a $100M+ federal grant contingent on an Alabama location; reworked the grant to allow a site change.

Water / Power

12" water line sufficient. Power: 5 MW currently available; 54 MW ultimate load requires a new transformer and two dedicated lines - est. $7,000,000, 3-year timeline, via Bluebonnet Electric Coop at $0.071/kWh. Wastewater contingent on the new SH-80 Lift Station (conservative Q1 2028 / best case Q4 2027).

Building Height Conflict

Company's stated need was a 60–70 ft max building/stack height - exceeding the site's own 62 ft ordinance cap (Development Code §4.4.5.4) even before the covenant issue arose.

City of San Marcos Response

Helen Ramirez (Director of Economic & Local Business Development) told HCEDP on May 8, 2026: "Given the covenant restrictions on the property we do not see this project being viable at Axis site." This matches the Development Agreement's Exhibit D prohibited-use list, which expressly bars "Manufacturing of carbon batteries" - the rejection rationale is consistent with the actual governing document.

  • Internal city discussion preceded the "official" rejection: Asst. Director of Engineering Richard Reynosa wrote April 24 that the project "is not going to pass City Council authorization for any kind of Economic Incentive," and Assistant City Manager Rodney Gonzales cited an unwritten policy against assisting "projects and business types that are intentionally excluded in our Economic Development Policy" to avoid "a false signal of supporting these types of projects."
  • Site-selection documents (JLL RFI log, 54 items) independently flagged San Marcos Regional Airport proximity as a potential "fatal flaw," and pegged overall site buildability at "~83%."
  • Senior Planner Julia Cleary noted only ~700 of the ~1,980–2,000 marketed acres are currently annexed/zoned into the City - a gap between marketed scale and actual jurisdiction.
Source: Allied Graphite Business Deck, JLL RFI/Site Assessment logs, city email correspondence, April–May 2026

Project Roller Coaster

Not Recommended - Water Demand Semiconductor Manufacturing
RFI Date: April 30, 2026
Investment: $10,000,000,000
Jobs: 5,100 FTE
Site Need: 400+ acres
NAICS: 334441

Water / Wastewater

15,400,000 GPD water / 11,900,000 GPD wastewater - the single largest water demand of any project in the pipeline, exceeding even Project Horizon Mill B's 9 MGD.

Power

500 MW by 2030 / 425 MW peak - an extraordinary transmission-scale demand.

Timeline

Company deadline of May 12, 2026 for a response.

City of San Marcos Response

Richard Reynosa: "You are correct we would not recommend pursuing such a large water user." A $10B, 5,100-job project - by far the largest in the pipeline by investment - was turned away purely on water infrastructure grounds.

Source: Governor's Office RFI documents, April 2026

Project Fiber Optics

Deadline Missed / Undocumented Fiber Optics Manufacturing (Japanese company)
RFI Date: April 17, 2026 (same-day 5pm deadline)
Investment: $626M–$1,566M
Jobs: 600
Site Need: 50+ acres greenfield
NAICS: 33592

Water / Wastewater

~503,000–507,000 GPD water (figure inconsistent across the document); 480,794 GPD sewage. Process includes a "wet scrubbing tower" generating industrial sludge.

Power

30 MW / 150 GWh per year.

Site Competition

Sarah Martin (HCEDP): the TriTexas/Axis site is "the only eligible site for Heavy Industrial Zoning" for this project regionally.

City of San Marcos Response

Same-day RFI deadline (4/17, 5pm) - no documented city response or submission outcome found in the released records.

Source: Governor's Office RFI documents, April 2026

Project Neighborhood Club

Active - Requirements Could Be Met Critical Minerals Processing / Recovery
RFI Date: April 30, 2026
Investment: $650M ($250M building / $350M equipment)
Jobs: 300 → 350 ($75,000 avg.)
Site Need: 1,000 acres greenfield
NAICS: 335910

Water / Wastewater

414,625 GPD water; 365,069 gal/month wastewater.

Power

25 MW by August 2029.

City of San Marcos Response

Richard Reynosa: "These requirements could be met." One of the more straightforward feasibility assessments in the pipeline.

  • Critical minerals processing/recovery aligns with federal supply-chain security priorities, similar in strategic framing to Project North Star (rare-earth-free magnets).
Source: Governor's Office RFI documents, April 2026

Project Skate Board

Unresolved - Chemical Process Uncertainty Aerospace / Defense - Advanced PCB Manufacturing (Turkish company)
RFI Date: April–May 2026
Investment: $80,000,000 (financing not yet secured)
Jobs: 150 → 220 ($65,000 avg.)
Site Need: 25 acres
NAICS: 334412

Operations

Turkish aerospace/defense company manufacturing advanced multi-layer (8–32 layer, HDI) printed circuit boards. Company reported lacking full project funding and is seeking equity/partnership financing.

Water / Wastewater

1,500,000 gal/month (~50,000 GPD), industrial - requires pretreatment.

Covenant Risk

PCB wet-etch processes typically use acidic/alkaline etchants, and "Acid manufacturing" is a prohibited use under the Development Agreement. Director of Planning Terry Floyd thought the project could be supported under Permitted Use #30 ("Electronic Assembly/High Tech Manufacturing") but flagged uncertainty over the actual chemical process involved.

City of San Marcos Response

Unresolved as of May 4, 2026 - city staff have not determined whether the etching chemistry would trigger the acid-manufacturing prohibition.

Source: Governor's Office RFI documents, April–May 2026

Project Haute Couture

Low-Credibility Lead Textile / "Fashion City" Manufacturing Concept (Portuguese)
RFI Date: April 1, 2026
Claimed Investment: $61M - or "€4,691 BILLIONS" (as stated in the same document)
Claimed Jobs: 100,000–150,000
Site Need: 2,500 acres

Credibility Flags

The RFI's own investment and jobs figures are wildly internally inconsistent (a €4.69 trillion figure appears in the same document as a $61M figure). Claimed job counts (100,000–150,000) would exceed the entire population of San Marcos.

City of San Marcos Response

Helen Ramirez: "Given requested looks like Axis, but there are flags such as not having the necessary funds for the project." No submission outcome documented - treated as not credible.

  • Job and investment figures excluded from this page's pipeline totals due to internal inconsistency / lack of credibility.
Source: Governor's Office RFI documents, April 2026

Project Hat Trick

No Submission - Prohibited Use Metal Smelting (Aluminum / Copper / Steel Scrap)
RFI Date: April 10, 2026
Investment: $100,000,000
Jobs: 100 → 500 ($60,000 avg.)
Site Need: 20 acres
NAICS: 331314

Water / Power

4,000,000 gal/month (~150,000 GPD) water; 10 MW power.

City of San Marcos Response

Sarah Martin (HCEDP): "we will not be submitting for Project Hat Trick... the project industry of smelting Iron, Tin, Zinc Copper or other ores is listed under the site's prohibited uses." Directly confirms enforcement of the Development Agreement's prohibited-use list, which expressly bars "Smelting of iron, tin, zinc, copper or other ores."

Source: Governor's Office RFI documents, April 2026

Project Ellie

Interest Expressed Aviation - VTOL Aircraft Manufacturing & Flight Test
RFI Date: April 20–21, 2026
Site Need: 75,000 sf building → path to 550,000 sf
NAICS: 336411

Operations

VTOL (vertical takeoff and landing) aircraft manufacturing plus an on-site flight-test facility, requiring FAA-approved UAS airspace - ties into the site's airport-adjacent I-Zone.

City of San Marcos Response

Helen Ramirez: "We are interested. Airport Axis can be manufacturing and possible testing." Financial and utility detail were contained in an RFP attachment not captured in the released correspondence.

Source: Governor's Office RFI documents, April 2026

Project Apex Prime

Declined - May 2026 Food / Agriculture - Wheat-to-Pasta Processing (Turkish company)
RFI Date: May 6–11, 2026
Investment: $180,000,000
Jobs: 180 → 500
Site Need: 60 acres
NAICS: 311824

Operations

165,000 metric ton/year pasta production capacity.

Water / Wastewater / Power

8,000,000 gal/month (~300,000 GPD) water; 750,000 gal/month wastewater; 15 MW peak (2029) / 8 MW day-one.

City of San Marcos Response

Helen Ramirez: "we do not think it fits" on environmental grounds. Sarah Martin confirmed: "We will not submit the TriTexas site." This RFI, dated May 11, 2026, is among the first documents to use the "TriTexas" name for the site, contemporaneous with the May 4–5 rebrand.

Source: Governor's Office RFI documents, May 2026

Project Sling Shot

Pending - No City Response Documented Steel Pipe Manufacturing / Coating (Mexican company)
RFI Date: May 18–19, 2026
Investment: $120,000,000 ($50M land / $24M building / $46M equipment)
Jobs: 400 → 680 ($55,000 avg.)
Site Need: 120 acres
NAICS: 331210

Water / Power

575,895 gal/month (~23,035 GPD) water; power 11 MW peak / 5 MW day-one at 110,000V transmission.

City of San Marcos Response

Sarah Martin: "I wanted to see if San Marcos would like us to submit TriTexas for Project Sling Shot" - no city response documented in released records yet.

Source: Governor's Office RFI documents, May 2026
Key Intermediaries
Hays-Caldwell Economic Development Partnership: Sarah Martin and Emily Mathes served as local contacts coordinating with the Governor's Office on all RFIs.
Texas Governor's Office EDT Staff: Philip Rocha, Lauren Slusher, Jennifer Kolbe, Stephanie Mazurkiewicz-Muehlstein, Joe Magruder, and Sandra Sanchez distributed and managed RFIs.
City of San Marcos: As of spring 2026, Helen Ramirez (Director of Economic & Local Business Development) became the primary city-side contact fielding nearly all new RFIs, replacing the more distributed engineering/planning intake seen in earlier projects.
RFI Process: Companies respond to Texas Governor's Office Requests for Information (RFIs) specifying site requirements. The Governor's Office forwards these to local EDPs who gather city utility confirmations and submit formal responses.
Unresolved leads worth a follow-up PIR
Project Super Nova (site tour April 15, 2026): scheduling correspondence only, no financial detail released. Notably confirms Axis/TriTexas was one of four San Marcos sites shortlisted for this project (with San Marcos Business Park, Loop 110 Industrial Park, and McCarty Park), out of seven shortlisted regionally including Lockhart sites.
"Project Bushwood": named only in the Economic Development San Marcos (EDSM) Board's January 28, 2026 minutes, discussed in executive session under Tex. Gov't Code §551.087 (economic development confidentiality). No public detail on the project itself, and it is not confirmed to be related to TriTexas/Axis at all - a targeted PIR to the City or EDSM specifically for "Project Bushwood" records would be needed to determine that.
Compiled from City of San Marcos public information request documents - TriTexas Logistics Park (formerly SMART Terminal / Axis Logistics Park) project.
All information derived from records obtained through public information requests. Investment, jobs, and water figures are as stated in RFI documents.